Modular Interiors by Cook’s was contracted by the University of Calgary to replace approximately 1,000 square feet of raised access flooring at the Math Sciences Research Data Centre in Calgary, Alberta. The scope includes removing the existing floor, supplying and installing ASP Icon Data 1250 panels, and adding a new ramp and two steps.
In a data centre, the space beneath a raised floor can be as important as the surface itself. It provides room for building services and a path for airflow, while removable panels let facilities teams reach those services for maintenance. At the University of Calgary, the floor replacement also provided an opportunity to address unused infrastructure while the area beneath the floor was exposed.
A two-phase approach to floor replacement
The project scope calls for two phases, with approximately two weeks between removal of the existing floor and installation of the new system. During the first phase, our team removes the existing raised access flooring and handles waste and recycling. A temporary polyethylene barrier beneath the floor helps maintain static pressure during demolition.
The break between phases gives the university’s Data Centre Operations team access to unused electrical circuits and mechanical connections. With the panels out of the way, the team can address those items before the new floor goes in. Building that time into the schedule lets the flooring work and the university’s underfloor work proceed in sequence.
ASP panels for the data centre environment
The replacement floor uses ASP Icon Data 1250 raised access floor panels with a high-pressure laminate (HPL) finish. The scope pairs solid panels with two types of perforated panels to accommodate different airflow needs across the floor.
Select perforated aluminum panels feature adjustable dampers, which allow the facilities team to regulate how much air passes through those locations. The scope also includes perforated panels without dampers for locations where that adjustment isn’t required. Together, these configurations let the floor serve as both a working surface and part of the data centre’s air distribution system.
Transitions and long-term maintenance
Our scope includes supplying and installing a 5-foot-by-8-foot ramp and two steps to provide transitions to the raised floor. The university also receives 10 spare solid panels, giving its facilities team matching replacements to keep on hand for future maintenance.
The new system preserves access beneath individual panels, where electrical and mechanical services can be inspected or maintained as needed. For the University of Calgary, the project pairs an updated floor surface with practical access to the infrastructure the data centre depends on.